Enjoy these tips, tricks and insights that answer 100's of questions we've received from radiology and imaging professionals that need help buying, selling, servicing and maintaining their medical imaging equipment: MRI, CT, C-Arm, Digital X-ray, PET/CT and Women's Health. We extend the life of imaging equipment so that health care providers worldwide can extend the lives of patients. This is why we answer your imaging equipment questions.

~ Block Imaging Team

Relocating Your CT Scanner: What You Need to Know

Posted by Simeon Lowe

Aug 2, 2017 4:29:38 PM

CT Relocation.jpgIf you're considering relocating your current CT scanner, you're probably already aware that it's a move that can save you significant dollars and improve the care you're able to deliver across multiple facilities. If it's your first time relocating, however, you may not be aware of all of the steps, requirements, and "moving parts" of a project like this.

As an equipment and service provider, Block Imaging has performed hundreds of imaging system relocations over the last 20 years. To help you better prepare for your upcoming relocation, we'll share below some of the tips and pointers first-time relocaters need in advance for a smoother CT move and a quicker turnaround to installation and scanning in the system's new home.

Site Preparation

Regardless of whom you select to perform your relocation, the onus for proper room preparation and/or build-out generally falls to the management at the site. When relocating your CT, it’s crucial to make sure you get appropriate consultation regarding the new space it will be moving into. Electrical and mechanical requirements will vary based on the specific model of your CT scanner, so be sure to include an electrician and communicate with them closely throughout your preparations

Consider these questions:

  • What power connections does your CT require?

  • Is the incoming CT system air-cooled or water-cooled? What HVAC or plumbing essentials need to be considered to accommodate cooling?

  • What are the gantry dimensions, weight, and table movements? Will there be sufficient clearances for all movements?

  • What are the clinical functions that need to be taken into consideration as the layout is designed?

  • Does the incoming system have clear egress and ingress from the old room to the new room? Door sizes, hallway setup, and patient/staff traffic are all things that need to be considered as you plan the smoothest path of exit and entry.

If handling the preparation phase of a CT relocation sounds like a lot of work, that's because it is.There are many elements to keep track of. Fortunately, some service companies offer project management assistance to help guide you through the process. We can't speak for all providers, but Block Imaging's Project Management team can assist in everything from site drawings, to a system demonstration of use the day it installs. Consider working with a provider that has dedicated project management staff.

What full imaging equipment project management includes

The Timeline

We hate to say it, but the timeline of a relocation can vary significantly based on a few different things. We've seen facilities do all of the below, none of the below, and everything in between. Believe us- every item on this list plays a big part in determining the final span of the project.

  • Hire a quality engineer or service organization. Without the proper tools, dollies, packaging,  and de-installation and installation procedures, a CT relocation can turn into a nightmare quickly. Make sure the engineers performing this project have experience. Don't hesitate to ask for references!
  • Double (even triple)-check your room readiness. A properly prepared space makes everyone’s life easier. You would be shocked at how many times we’ve gotten a CT to its new home only to find out it is still under construction. We strongly recommend that you have a room readiness inspection by the installing engineer prior to delivery of the system.
  • Account for travel time- and be conservative about it. It may seem like common sense but, often, the time involved in physically transporting the system is not taken into consideration when forecasting the timeline of a CT relocation. If you’re moving a system across a state or three you’ll be looking at a much longer transit time than moving it from a hospital to the outpatient center in the next town.

In the long run, if rooms are ready, there are at least two knowledgeable engineers involved, and transit time is not a factor (or is counted separately), the mechanical side of a CT relocation project commonly takes between three and five days, including de-installation, re-installation, and calibration.

The Cost

Unfortunately, preparing a cost estimate for a relocation is not a cut-and-dry matter either. The price for most CT relocations will fall between $15,000 and $25,000 depending on the distance of transit. A system moving across the hall or down a couple of floors, for example, will fall on the lower end of that range, while a system crossing states or whole regions will fall on the higher end.

The most important thing you can do to keep costs lower for your relocation project is to follow the tips above. Vendor homework, careful room preparation, and clear communication keep things running on time and help all parties concerned avoid costly delays.

The Takeaway

CT scanner relocation has a lot of advantages for healthcare systems that operate multiple facilities. At the same time, relocation is a process that can get hectic and, without close management, more costly than anticipated. If keeping track of all the aspects we mentioned above seems like a recipe for frustration to you, we're ready to help. Our team has years of experience and dedicated project management staff that can work alongside you to make your project a success and keep costs down. Use the button below to tell us about your project and how we can help make it happen.

Free Consultation for Your Equipment Relocation Project

.........................

Written by Simeon Lowe

lowe-simeon

Simeon Lowe is the Director of Service at Block Imaging. He loves snowboarding, playing music, Godzilla movies, and the Detroit Lions. He also loves helping customers through their toughest equipment disasters with calmness and efficiency, so they can get back to serving the patients that rely on them.

 

Topics: Imaging Equipment Project Management, CT Scanner

    

Post a Comment Here

Search this site
Loading

Get medical imaging equipment insights delivered straight to your inbox. Subscribe below.

Resources
Meet the Block Imaging Team
Meet the Block Imaging Team

Questions? Ideas? Imaging project you'd like to discuss? Let us know!